To be fair, given the Collins-class issues, this is a pretty good improvement on refurb performance.

HMAS Farncomb arrived for maintenance in late May 2014 and is the first Collins Class submarine to undergo the new and revised maintenance regime since the Coles Review into submarine sustainment.

Previously, a full cycle docking of a Collins Class submarine could take in excess of three years; but HMAS Farncomb is on track to be completed in less than two years.



.