Finding A
Insufficient progess has been made toward implementation of the critical safetry item program
Finding B
Oversight of product development and realization of requirements was inadequate
Finding C
The quality assurance organization was not independent and not adequately staffed
Finding D
Reduction of the assembly defect rate was inadequate
Finding E
Corrective action request escalation was inadequate
Finding F
Software quality management was insufficient
Find ing G
Subcontract management procedures were still inadequate


--