F-35 Software Running as Much as 14 Months Late, Pentagon Finds
2014-07-29 20:44:46.772 GMT
By Tony Capaccio
July 29 (Bloomberg) -- Software needed to operate Lockheed Martin Corp.’s F-35 jet, the Pentagon’s costliest weapon system, may be as much as 14 months late for required flight testing, according to a Pentagon review.
The projected delay to September 2017 concerns the final version needed to provide full combat capability for Air Force, Navy and Marine Corps variants of the fighter, the Defense Department found in the report mandated by Congress.
"Delivering code" is not the same as it working in a final, go-to-war configuration.
---
-Time's Battleland - 5 Part series on F-35 procurement - 2013
-Summary of Air Power Australia F-35 points
-Bill Sweetman, Aviation Week and the F-35
-U.S. Government Accounting Office (GAO) F-35 reports
-F-35 JSF: Cold War Anachronism Without a Mission
-History of F-35 Production Cuts
-Looking at the three Japan contenders (maneuverability)
-How the Canadian DND misleads the public about the F-35
-Value of STOVL F-35B over-hyped
-Cuckoo in the nest--U.S. DOD DOT&E F-35 report is out
-6 Feb 2012 Letter from SASC to DOD boss Panetta questioning the decision to lift probation on the F-35B STOVL.
-USAFs F-35 procurement plan is not believable
-December 2011 Australia/Canada Brief
-F-35 Key Performance Perimeters (KPP) and Feb 2012 CRS report
-F-35 DOD Select Acquisition Report (SAR) FY2012
-Release of F-35 2012 test report card shows continued waste on a dud program
-Australian Defence answers serious F-35 project concerns with "so what?"
-Land of the Lost (production cut history update March 2013)
-Outgoing LM F-35 program boss admits to flawed weight assumptions (March 2013)
-A look at the F-35 program's astro-turfing
-F-35 and F-16 cost per flying hour
-Is this aircraft worth over $51B of USMC tac-air funding?
-Combat radius and altitude, A model
-F-35A, noise abatement and airfields and the USAF
-Deceptive marketing practice: F-35 blocks
-The concurrency fraud
-The dung beetle's "it's known" lie
-F-35's air-to-air ability limited
-F-35 Blocks--2006 and today
-The F-35B design is leaking fuel
-F-35 deliveries
-ADF's wacky F-35 assumptions