Quick review of some but not all F-35 LRIP-6 costs via U.S. DOD contracts thus far:
Not counting jet engines and and maybe some other future things, thus still a work in progress. Some of this money was not mentioned the other day when the fan-base-news stated a 4pc. reduction for LRIP-6 vs. LRIP-5. A WAG on jet engines for the future PW order to support LRIP-6 are $38M each per STOVL and $13M or more each for non-STOVL. None of this counts the total cost to get the jet into squadron service. Note: total airframe numbers still could change.
Date of DOD contract/Type/$M
8Aug11/Advance acquisition contract/535.3
6Jan12/Advance acquisition contract/194
9Feb12/STOVL long-lead/14.8
12Mar12/CTOL long-lead for USAF, Australia, Italy/38.59
6Dec12/Sustainment support/386.69
28Dec12/18CTOL,6STOVL,7CV/3677.9
5Mar13/Support equipment including Australia, Italy/72.2
12Aug13/Special tooling and test equipment/852.29
sub-total $5771.77M
Oh yeah, and whatever the lift-systems contract by Rolls-Royce ends up as for the STOVL aircraft.